The SledTred™: Assembly Guide

The SledTred™: Assembly Guide

Step 1: Installing the Flywheel and Rear Roller Covers

Required Components:

Tread deck

Flywheel covers

Rear roller covers

M5*8 screws

1. Align the flywheel cover with the holes on the treadmill deck.

2. Secure the cover using the provided screws and tighten them with the included tool.

3. Repeat the process for the other side.

4. Slide the rear roller cover into position and screw it into place.

Step 2: Attaching the Upright Frames

Required Components:

Base frame

Upright frames

(8) M8*55 bolts with washers and nuts

1. Remove the protective plastic from the side rail.

2. Position the upright with the resistance dial on the right side of the frame.

3. Align the holes and insert the bolts.

4. Place a washer and nut on each bolt.

5. Use the provided wrench and Allen key to tighten securely.

6. Repeat the process on the other side.

Step 3: Installing the Tread Deck

Required Components:

Treadmill deck

(2) M10*65 bolts with flat washers

1. Align the tread deck with the entry points inside the upright frame.

2. Insert and tighten the bolts on each side using the provided Allen wrench.

3. Use the provided Allen wrench to fully secure the tread deck.

Step 4: Installing the Plastic Adapters (Without Power Tower Model Only)

Required Components:

Plastic adapters

(2) M8*40 bolts with washers and nuts

1. Place the plastic adapter on top of the upright frame.

2. Insert an M8*40 bolt through the first hole and secure it with a washer and nut.

3. Tighten securely and repeat for the other side.

Note: If upgrading with a power tower, remove the three bolts, take out the plastic adapter, and proceed to Steps 5–7.

Step 5: Installing the Multi-Grip Support Bar

Required Components:

Power tower support bar

Power tower uprights

(2) M8*40 bolts with washers

1. Insert a bolt through the side of the power tower frame.

2. Secure it to the support bar.

3. Repeat for the other side.

Step 6: Installing the Multi-Grip Chin-Up Bar

Required Components:

Multi-grip chin-up bar

(4) M10*100 bolts with curved washers and nuts

1. Insert a bolt through the bottom of the frame and the chin-up bar.

2. Attach a curved washer and nut to the bolt.

3. Repeat for the lower hole.

4. Complete the process on the other side.

5. Tighten all six bolts securely.

Step 7: Installing the Monitor Frames

Required Components:

Upper and lower monitor frames

Power Tower Attachment

(2) M8*15 bolts with round washers

(2) M8*75 bolts with round washers

1. Insert the Power Tower Attachment into the upright frames.

2. Assemble the lower monitor frame and hand-tighten the bolts.

3. Repeat for the upper monitor frame.

4. Secure the lower monitor frame using two M8*75 bolts with washers, ensuring the bolts face downward.

5. Tighten all bolts using the provided tools.

6. Secure the upper monitor frame with four M8*50 bolts and flat washers.

Step 8: Attaching the Sled Push Pads

Required Components:

Sled push pads

M8*40 bolts with round washers

1. Slide the push pads onto the middle bars.

2. Attach them to the upper and lower monitor frames using M8*40 bolts and washers.

3. Secure the bolts from the inside of the SledTred™ outward.

4. Repeat on the other side.

Step 9: Securing the Power Tower Attachment

Required Components:

M8*40 bolts with washers and nuts

M8*15 bolts with curved washers

1. Insert an M8*40 bolt through the power tower from the inside out.

2. Secure it with a washer and nut.

3. Repeat for the other side.

4. Use an M8*15 bolt and curved washer to attach the uprights.

5. Repeat the process on the other side.

Step 10: Installing the Multi-Pad

Required Components:

The multi-pad

(2) pull knobs

1. Insert the pull knobs into either side of the multi-pad.

2. Pull back on the knobs and attach the multi-pad to the uprights.

3. Tighten all console frame and power tower bolts.

4. Remove the multi-pad.

5. Lift the treadmill deck and secure it using the long storage knob.

Step 11: Installing the Resistance Cable Wire

1. Insert the end bead into the upper cable connector.

2. Pull back on the threaded end of the lower flywheel cable and insert it into the forked bracket.

3. Securely tighten the loose nut onto the threading.

Step 12: Securing the Multi-Pad

1. Pull both pull knobs and attach the multi-pad to the frame.2.Screw in a knob on either side to secure it.

Step 13: Installing the Dip Bars

Required Components:

Right and left dip bars

Pull knobs

Screw knobs

1. Take a pull knob and screw it into the bottom of the right dip bar.

2. Pull back on the knob and attach the dip bar to the frame.

3. Secure the top hole with a screw knob.

4. Repeat for the left dip bar.

Step 14: Installing the Monitor

1. Place the monitor on the monitor stand and press down to secure it.

2. Connect the two wires together.

3. Connect the wires on the left side of the SledTred™.

4. Attach the sensor to the sensor clip, ensuring it is approximately half an inch from the flywheel.

5. Tuck the excess wire into the uprights.

Additional Resources

For more exercises and training ideas using The SledTred™, check out the Training Collective.

Need Assistance?

If you have questions about The SledTred™ or need help with your exercises, feel free to reach out to our support team at HERE

Reading next

The Best Bulletproofing Lower Body Fitness Accessory?

Leave a comment

All comments are moderated before being published.

This site is protected by hCaptcha and the hCaptcha Privacy Policy and Terms of Service apply.